Prismatic Development Corp is a general contracting and construction firm founded in 1983 and based in Fairfield, New Jersey, that has built public works projects for agencies including the New York City Department of Sanitation and the New York City Economic Development Corporation. It has registered as a citywide lobbying client in New York City from 2024 through 2026, filing 14 disclosures through Constantinople & Vallone Consulting LLC and paying $75,000 in compensation, with its subjects covering city budget matters tied to infrastructure and real estate development. It holds an active New York City contract valued at about $120 million as of August 2026.
- Council members lobbied
- 51 (citywide)
- Filings (since 2024)
- 15
- Lobbying compensation (since 2024)
- $80,000
- Industry (per city contracts)
- Construction Services
- City contracts (active)
- $120,023,800 · 2 contracts
- Awarded all-time
- $589,179,011 · 5 since 2009, incl. expired
- Paid to date
- $469,974,794
- Based in
- Fairfield, NJ (out of state)
Represented by lobbyist firms
- Constantinople & Vallone Consulting LLC Lobbyist firm
Holds contracts at
- Department of Citywide Administrative Services City agency
- Department of Design and Construction City agency
- Department of Sanitation City agency
Funded by these agencies
- Department of Citywide Administrative Services City agency
- Department of Design and Construction City agency
- Department of Sanitation City agency
What they lobbied on
subjects from their filings
- Budget - Connecting to infrastructure-related development opportunities and Covid-related stimulus opportunities
- Budget - Infrastructure
- Budget - Real Estate/General
City contracts
Registered city contracts, largest first by current contract value (not amount spent): running now, then registered to start later, then ended. Totals count every registered contract. Each line shows its Checkbook contract ID. The tag on each row is how it was awarded (“no-bid” = non-competitive).
- 1 Centre Street Elevator Modernization Department of Citywide Administrative Services · CT185620268807910 $73,879,000
- Encumbrance increase. Department of Sanitation · CT182720258809284 $46,144,800
- CONVERSION PROGRAM NORTH SHORE MARINE TRANSFER Department of Sanitation · CT182720100004760 · ended 2015 $164,556,364
- Staten Island 1 & 3 Garage, Phase 2 Department of Design and Construction · CT185020211414552 · ended 2026 $153,897,492
- SOUTHWEST BROOKLYN MARINE TRANSFER STATION Department of Design and Construction · CT185020141418737 · ended 2018 $150,701,354
Largest payments, by purpose
The organization's largest individual city payments (roughly $25,000 and up), grouped by purpose, to show what recent money was for. This is NOT a total — smaller payments aren't listed; see “Paid to date” above for the complete amount paid against its contracts. Fiscal years 2020 and later.
- Staten Island 1 & 3 Garage, Phase 2 Department of Sanitation · FY2024 · 18 payments $35,970,808
- Staten Island 1 & 3 Garage, Phase 2 Department of Sanitation · FY2025 · 25 payments $28,217,746
- Staten Island 1 & 3 Garage, Phase 2 Department of Sanitation · FY2023 · 17 payments $27,666,407
- Staten Island 1&3 Garage, Phase 2 Department of Sanitation · FY2022 · 9 payments $18,667,669
- Staten Island 1 & 3 Garage, Phase 2 Department of Sanitation · FY2026 · 15 payments $6,482,665
- Staten Island 1 & 3 Garage, Phase 2 Department of Citywide Administrative Services · FY2025 · 18 payments $3,323,631
- Staten Island 1 & 3 Garage, Phase 2 Department of Sanitation · FY2022 $2,650,003
- Staten Island 1 & 3 Garage, Phase 2 Department of Citywide Administrative Services · FY2023 · 11 payments $2,280,986
- Staten Island 1 & 3 Garage, Phase 2 Department of Citywide Administrative Services · FY2024 · 11 payments $1,544,000
- Bx 12 Garage Rehabilitation and Construction of FEMA Shed Department of Sanitation · FY2026 $1,224,821
- Staten Island 1&3 Garage, Phase 2 Department of Citywide Administrative Services · FY2022 · 7 payments $900,947
- Staten Island 1 & 3 Garage, Phase 2 Department of Citywide Administrative Services · FY2022 $428,906
- SOUTHWEST BROOKLYN MARINE TRANSFER STATION Department of Sanitation · FY2020 · 3 payments $229,077
- SOUTHWEST BROOKLYN MARINE TRANSFER STATION Department of Design and Construction · FY2020 $41,824